The repair of unit 6 of the Kozloduy NPP has been completed

The unit is included in the electricity system

Nov 23, 2024 14:46 49

The repair of unit 6 of the Kozloduy NPP has been completed  - 1

On November 23, 2024. the planned annual repair of the sixth power unit of the nuclear power plant was completed and after an inspection by the Nuclear Regulatory Agency at 10:07 a.m. the unit was included in the country's electricity system.

During the downtime, which began on October 19, 2024, the activities planned for the repair campaign were carried out, as well as the planned measures related to increasing safety and long-term operation. The sixth unit reactor has been reloaded with fresh nuclear fuel for the next fuel campaign.

The necessary tests and inspections confirming the operability and reliability of the facilities were also successfully carried out.

According to the technological regulation, the loading of the block is carried out in stages.

Fifth power unit of NPP “Kozloduy” operates in accordance with the power generation schedule.