API admitted: 7 new landslides prevent the opening of traffic on the Mezdra - Botevgrad road

These are not the first landslides that appeared around the new route of the Mezdra - Botevgrad road

Nov 25, 2024 21:37 176

Seven newly appeared landslides obstruct the launch of the Mezdra road – Botevgrad at the end of the year.

These are not the first landslides that have appeared around the new route of the Mezdra - Botevgrad road. At the beginning of January this year, during a protest, residents of the village Rebarkovo reported a landslide in the area.

API announced that the builder informed them in March that there were four new landslides, one of which was at the "Rebarkovo" road junction.

This was announced by the "Road Infrastructure" Agency. (API).

The landslides are registered by "Geoprotection - Pleven" EOOD and "Geoprotection - Pernik" Ltd. in the last two months. Of these, five are along the route of lot 1 – in the section at the "Lutidol" road junction; and between Lutidol is. Nomination.

The other two are in the section of lot 2 – near the "Rebarkovo" road junction; and on the tour of the village. Lutidol.

According to the information provided by API about the new landslides, projects for strengthening and securing the rock slopes will be prepared and approved. At the same time, one of the tunnel facilities planned for the project will have to be extended by about 96 meters.

Therefore, until the start of the strengthening activities and the subsequent performance of all necessary construction and installation works, it will be necessary to continue with the temporary traffic safety organization in the section of the I-1 road.

On the website of the "Road Infrastructure" Agency a draft order on the temporary organization and safety of traffic during construction activities has been published for public discussion until December 22.

These are not the first landslides that have appeared around the new route of the Mezdra - Botevgrad road. At the beginning of January this year, during a protest, residents of the village Rebarkovo reported a landslide in the area.

API announced that the builder informed them in March that there were four new landslides, one of which was at the "Rebarkovo" road junction.

A procedure for selecting a contractor has begun, and the value of the public contract for strengthening and securing the landslides and unstable slopes along the route was over 63 million. BGN without VAT, for construction supervision - over 2 million BGN

On October 21, in a live broadcast on the Facebook page of GERB leader Boyko Borisov, the former regional minister Nikolay Nankov commented that in the project they commissioned for the Mezdra - Botevgrad road in 2019, there was no road junction near Rebarkovo. because they knew that the area was prone to landslides, BTA recalls.